Notable Features |
|
Steel structure with concrete
core |
|
Bonbed slabs |
|
Stone-clad precast façade |
|
Raised access floor |
|
Steel-clad metal demountable
partitioning |
|
|
Basic Information |
Location: |
Sheung Woo Che Road,
Pai Tau Street Shatin, New Territories, Hong Kong. |
Building Type : |
Office space |
Contract
Period: |
27 months. Began in
August 1999. Superstructure started in October 2000 |
Contract Sum : |
HK$780 million |
Architect : |
Architectural Services Department |
Main Contractor : |
Hong Kong Construction |
Façade
Technology
: |
Meinhardt Façade
Technology |
|
. |
Overview |
The
16-storey office building was built with a central concrete core and a steel
frame which supports profiled steel decking of the floor slabs. The main issues
considered were:
long life
(long-span steel frame), flexibility, a steel structure can achieve large spans
that maximize the flexibility for office space planning, and energy
conservation.
Flexibility was achieved with the omission of intermediate columns and with the
use of the raised floor system and demountable partitions. The building is more
adaptable to new users and therefore the life of the building is extended. Also
steel is recyclable.
This project
used design and built concept, and had the advantage that all members of the
team (design, production and construction) are as a whole, which eliminated many
contractual issues. |
|
|
|
Central Concrete Core and Steel Frame |
The 14m clear
span was achieved with less structural depth than with concrete, using high
strength steel beams, the webs of which also accommodated bigger voids for the
passage of services. |
|
|
|
|
Raised
Floor System |
|
The building
floor-to-floor height is 3,950 mm and the ceiling height is 2,500 mm, over a 200
mm raised floor. |
|
|
|
|
|
Stone-concrete Precast Panels |
|
|
The panels were fabricated in Yuen Long and transported to the site and
positioned. The stone from Italy, was assembled face down into the precast steel
mold. A joint seal was put between the stones. A plastic sheet and stainless
steel pins were disposed and concrete was poured. There are over a thousand
panels with a maximum weight for the largest one of 12 tonnes. They were hoisted
up and clipped onto adjustable steel brackets, secured from within. The erection
was possible without scaffolding and no stone workers were required on-site. |
|
|
The stone-clad precast
facades |
Advantages : |
- Ease of installation |
- Safety |
- Uniformity |
- Durability |
- The system reduces
the need for steel in
the outside environment |
|
Disadvantages : |
-
Heavier
system increasing loads to the
columns and
the foundations. |
-
Should be
considered at an early stage
of design, as
the building frame should be
pre-designed to accommodate this
additional façade loading |
|
Contact of
Contractor |
Hong Kong
Construction
http://www.hkconstruction.com
Rm 801,2
East
Ocean Centre
98 Granville Road,
Kowloon, Hong Kong
Tel:
(852)
2369 3949
Fax:
(852) 2721
5110
Email:info@hkconstruction.com |
|
|
Sources |
-
Ralph T.,
Charting New Territories,
Shatin Government offices, Asian
Architect and Contractor. |
-
Ralph T., The
long view from Shatin,
Shatin Government offices, part II,
Asian Architect and Contractor. |
-
Summary of major construction
projects,
Hong Kong Construction
(Holdings) Ltd:
http://202.66.146.82/listco/hk/hkconstruction/annual/
2001/sum.pdf |
|
|
|
|