|
|
|
|
The Structure |
|
|
|
The need for
thermal mass is achieved through a concrete frame and ribbed-floor construction,
with the precast concrete providing the desired level of finish. The line
loading from the 3rd floor setbacks is minimized through the use of
structural steelwork and allows the depths of the main structural frame beams to
be maintained. The 15m spans forming the rungs are achieved by using
pre-stressed precast-concrete floor beams. |
|
The
repetitive structural system favoured prefabrication construction. Precast
“double tee” floor units have been adopted as a primary structural system. The
basic precast concrete module of 1.5m, reflecting the planning grid has been
detailed to achieve satisfactory joints between precast units (in-situ concrete
infills and fire-resistant sealants). The in-situ concrete columns in the
rotunda and core were built during the setting up of the prefabrication system. |
|
The precast
concrete structure and cladding allowed faster construction (20 months program).
40,000m2 of structure and cladding were erected in 26 weeks. |
|
|
|
Cost Analysis |
|
|
|
|
|
Cost
Summary |
|
|
|
|